Plan production for the October delivery peak
You are the production planner reporting to the Production Manager.
What has happened
October is the heaviest month of the year. The St Aidan's College blazers, the Harbourline front of house shirts, the Pinnacle Rail high visibility shirts and the Bassline boom covers are all due, the reflective tape for Pinnacle is still on order, one band knife is out of service, and the Merriwa aprons are on hold for fabric. The General Manager has approved a voluntary afternoon overtime crew from 5 October. She wants a two-week production plan that sequences the work orders through cutting, sewing and finishing, sets daily output targets, shows where the afternoon crew is needed and flags every material and machine constraint, for the leadership meeting on 15 September.
Deliverables
- Open work order and constraint schedule
- Capacity calculation for cutting and sewing
- Two-week production plan with daily targets and crew allocation
- One-page leadership summary
- Updated work order notes
Documents to use
- Quality Policy Policy
- Lay-up, Marking and Cutting Procedure Procedure
- WHS Management Plan 2026 to 2027 Plan
Systems to use
Production Work Orders
Tracks every production, sample and repair job from release through cutting, sewing, finishing and dispatch.
Tech Pack Register
Holds the product specification record for every style and controls which version Production is allowed to cut against.
Materials and Trims Stock
Keeps the stock record for fabric rolls, leather hides, trims, thread and chemicals with location, quantity and supplier compliance status.
Quality Inspection Log
Records receiving, cut, in-line and final inspections and the disposition of any nonconforming product.
Units of competency
Current on training.gov.au for the Textiles, Clothing and Footwear as at 10 September 2026.
MSTGN4019Plan and implement production within a work areaMSTGN3013Control production in a section of a TCF enterpriseMSTGN5012Participate in production planning processesMSTGN4014Produce and analyse spreadsheetsMSTGN3015Supervise operations in a TCF enterpriseQualifications
MST40222Certificate IV in Apparel and FashionMST50122Diploma of Apparel, Fashion and TextilesWhat to look for
Evidence guide
The plan must be built from the actual work orders, tech pack statuses and stock records on the site, with capacity figures that are calculated and stated. Look for constraints that are identified with actions rather than ignored, an honest statement of any date that cannot be met, and a summary a manager can act on. The work order notes must match the plan.